Concrete quantity for a slab

The concrete quantity for a slab is calculated using:

\[ \text{Concrete Quantity} = \text{Length} \times \text{Width} \times \text{Thickness} \]

All dimensions must be converted into metres.

Example

Suppose a slab has:

  • Length = 6 m
  • Width = 4 m
  • Thickness = 125 mm = 0.125 m

\[ \text{Concrete Quantity} = 6 \times 4 \times 0.125 = 3.00 \text{ m}^3 \]

Therefore, the required concrete volume is 3.00 m³.

Deducting Openings

If the slab contains an opening, deduct its volume.

For example, an opening of 1 m × 0.5 m is provided:

\[ \text{Opening Volume} = 1 \times 0.5 \times 0.125 = 0.0625 \text{ m}^3 \]\[ \text{Net Concrete Volume} = 3.00 – 0.0625 = 2.9375 \text{ m}^3 \]

Adding Wastage

Add approximately 3–5% for wastage, spillage and uneven surfaces:

\[ \text{Concrete to Order} = 2.9375 \times 1.05 = 3.084 \text{ m}^3 \]

Therefore, approximately 3.08 m³ of concrete should be ordered.

Important Notes

  • Convert slab thickness from millimetres to metres.
  • Calculate each slab panel separately if dimensions or thicknesses differ.
  • Beams should normally be calculated separately.
  • For an RCC beam passing through the slab, calculate only the portion below the slab to avoid double counting.
  • Reinforcement steel is usually not deducted from the concrete volume in normal quantity estimation.
  • For a sloping slab, use the average thickness:

\[ \text{Average Thickness} = \frac{\text{Minimum Thickness}+\text{Maximum Thickness}}{2} \]

Thus, the basic formula is:

\[ \text{Concrete Quantity} = \text{Length} \times \text{Width} \times \text{Thickness} \]

Tshering Dorji Changed status to publish