Last updated: 8 November 2026
1. Introduction
The Beipanjiang Bridge, commonly called the Duge Bridge and also identified as the Beipanjiang First Bridge, carries the Hangzhou–Ruili Expressway across the deep Beipanjiang gorge on the boundary between Guizhou and Yunnan provinces in southwest China. It is a two-pylon cable-stayed bridge with a steel truss main girder. Its 720 m central span and exceptionally deep valley crossing made the project a notable example of long-span bridge engineering in steep terrain. Read our guide on types of bridges based on superstructure.
The bridge opened to traffic on 29 December 2016. At opening, the roadway clearance above the river or valley floor was reported at approximately 565 m. Guinness World Records recognises it as the highest cable-stayed bridge, using a 565 m clearance at mean high water. In 2025, the Huajiang Grand Canyon Bridge superseded it as the highest bridge overall, later receiving Guinness certification at 626.01 m in 2026. The Duge record describes roadway clearance, not tower height or structural depth.
The engineering value of the project lies beyond its record height. The designers had to reconcile a long main span, steep and geologically complex terrain, access constraints, a locally complex wind environment and an erection strategy that could avoid relying on conventional ground-supported falsework across the gorge. The published engineering literature identifies the steel truss deck system, mountainous wind effects, girder erection and cable icing monitoring as project-specific technical subjects.
This case study reviews the known project facts, the documented structural arrangement and construction innovations, and the engineering principles that can be inferred from them. It does not reproduce original design calculations or assert performance data that are not available in the cited public sources.
2. Project overview
| Item | Reported information | Evidence status |
|---|---|---|
| Project name | Beipanjiang Bridge / Beipanjiang First Bridge; commonly called Duge Bridge | Confirmed in government, Guinness and engineering sources |
| Location | Across the Beipanjiang gorge between Duge, Guizhou, and Puli/Puli Township, Yunnan, China | Confirmed in project and government reporting |
| Route | Hangzhou–Ruili Expressway, also known as G56 | Confirmed in government reporting |
| Bridge type | Two-pylon cable-stayed bridge with a steel truss main girder and orthotropic steel deck | Engineering paper |
| Total bridge length | 1,341.4 m | Government/project reporting |
| Main span | 720 m | Engineering paper and government reporting |
| Main bridge span arrangement | (80 + 2 × 88 + 720 + 2 × 88 + 80) m | Engineering paper; this totals 1,232 m and should not be confused with total bridge length, which includes additional approach structure |
| Clearance | About 565 m above the river/valley; Guinness reports 565 m at mean high water | Guinness and government reporting; datum wording varies by source |
| Main girder | Steel truss with orthotropic steel deck | Engineering paper |
| Stay cables | 224 cables arranged as 112 pairs; anchored to steel beams in the pylons and steel anchor boxes at the upper truss chord | Engineering paper abstract |
| Towers | Reinforced-concrete H-shaped towers | Engineering paper abstract |
| Foundations | Group of 28 piles, each reported as 2.8 m diameter, for the bridge tower foundations | Engineering paper abstract; pile lengths and founding strata not stated in the abstract |
| Construction and opening | Major bridge works were underway by 2013; completed/closed for joining in September 2016; opened 29 December 2016 | Contractor/trade and government reporting; dates describe different milestones |
| Owner / implementing authority | The bridge forms part of the Guizhou section of the Hangzhou–Ruili Expressway. A definitive owner entity and formal project company were not established in the accessible primary documents reviewed for this article. | Not fully verified |
| Design consultant | CCCC Highway Consultants Co. (China Communications Construction Company Highway Consultants) is identified in Chinese project reporting as the design organisation. | Secondary project reporting; verify against primary project records before treating as contractual attribution |
| Main contractor | CCCC Second Harbour Engineering Co. is identified by construction trade reporting as the main contractor for the bridge build. Regional works involved other organisations. | Contractor/trade reporting; scope split not fully verified |
| Project cost | Not included. Media reports quote values above RMB 1 billion, but a complete official cost breakdown was not located. | Unverified for this case study |
| Main achievement | A 720 m steel-truss cable-stayed main span over a gorge with an approximately 565 m clearance; recognised by Guinness as the highest cable-stayed bridge | Confirmed by engineering and record sources |
The engineering paper’s span sequence describes the main cable-supported bridge portion. The sequence sums to 1,232 m, while the frequently reported 1,341.4 m total length includes approach bridge sections. Sources also vary in whether height is described above the river, gorge, valley floor or mean high water. For technical writing, state the measurement datum wherever it is known and avoid treating those terms as interchangeable.
3. Site location and environmental conditions
3.1 Geography and topography
The bridge crosses a deep, steep-sided gorge in the mountainous boundary region between Guizhou and Yunnan. The north-south or cross-valley route is constrained by high ridges and sharply sloping abutment areas. The unusually large vertical separation between the roadway and river means the bridge is not simply a high viaduct over a broad valley: its towers, foundations, access routes and erection logistics are concentrated on steep terrain above a narrow gorge.
The road crossing forms part of a regional expressway connection. Government reporting describes a substantial reduction in journey times between communities in the two provinces after the expressway opened. The project therefore combines a major transport function with a challenging site geometry.
3.2 Geology and geotechnical context
The project literature describes steep terrain variation and karst geology as important design and construction constraints. Karst ground can include irregular rockhead, solution cavities, fissures, variable rock mass quality and groundwater pathways. These conditions can make foundation investigation and construction less predictable than a uniform rock profile. The published summary confirms that complicated geology influenced project studies, but it does not disclose the borehole logs, discontinuity mapping, cavity treatment records, pile socket lengths, foundation design parameters or slope-stability analyses.
The documented tower foundation arrangement comprises a group of 28 large-diameter piles, measuring 2.8 m in diameter, as described in the published engineering paper. This fact should not be stretched into claims about pile depth, socket length, pile capacity or the geology at each pile location. Those details require the original geotechnical and foundation records.
3.3 Seismic, wind and climate considerations
The engineering literature specifically reports studies of wind loading in mountainous terrain. This is significant because ridges and gorge geometry can channel, accelerate, separate or locally redirect airflow. Terrain-induced turbulence and directionality may make a simple flat-terrain wind assumption inadequate. The available source does not publish design wind speeds, aerodynamic derivatives, wind-tunnel results or the governing code provisions.
The available project summary does not provide the site-specific seismic hazard, response spectra, design earthquake level, ductility detailing assumptions or seismic analysis results. Seismic design is an essential consideration for a long-span bridge in a mountainous region, but project-specific values cannot responsibly be stated from the accessible material. The source does identify monitoring related to cable freezing during operation, which indicates that icing was considered an operational issue; it does not disclose the design ice load or full environmental design envelope.
3.4 Access and logistics
Construction access was difficult because the site is remote, elevated and reached by narrow winding mountain roads. A report on tower construction notes that tower cranes and other heavy equipment had to be transported over 2,000 km, with a substantial part of the route on narrow, winding roads. The gorge made conventional falsework from the riverbed impractical. These constraints affected equipment selection, delivery size, lifting strategy, temporary works and safe work planning at height.
4. Structural configuration and design concept
4.1 Structural system
The main bridge is a two-pylon, two-cable-plane cable-stayed structure with a steel truss girder. The main span is 720 m, with shorter side spans and approach structures. Its reported main-bridge span sequence is 80 + 88 + 88 + 720 + 88 + 88 + 80 m.
The deck is formed by a steel truss supporting an orthotropic steel deck. An orthotropic deck uses a steel deck plate stiffened in one direction by longitudinal ribs and supported by transverse members. It can provide a relatively light roadway deck, while the truss supplies longitudinal stiffness and creates a load path for global bending, shear and axial forces.
The two H-shaped reinforced-concrete towers support paired planes of stay cables. The engineering paper reports 224 cables, or 112 pairs. Each stay connects a steel anchorage beam in a tower to a steel anchorage box on the upper chord of the truss. Cable forces therefore enter the deck through the truss chord and enter the tower through the anchorage beam and tower legs/cross-members.
4.2 Load-transfer explanation
A simplified load path is:
- Vehicle wheels apply concentrated loads to the orthotropic deck plate.
- Deck plate stiffeners and transverse members distribute wheel loads into the steel truss.
- The truss carries longitudinal bending, shear and axial force, while its joints and chords transfer force to stay-cable anchorages and bearings.
- Stay cables carry primarily tension and support the deck at a series of points, reducing the unsupported bending length of the girder.
- Cable forces transfer into the reinforced-concrete towers, which carry compression and bending to the foundations.
- Tower and bearing reactions pass into the pile groups and surrounding ground.
The cable-stayed system is efficient for a long crossing because it supports the deck continuously through inclined stays instead of requiring a deep foundation or support in the gorge. The steel truss provides a stiff, triangulated main girder that can be assembled from prefabricated segments and can accommodate a long span with reduced self-weight compared with an equivalently stiff solid girder. These are general structural interpretations, not reported project calculation results.
4.3 Balance and anchorage
The design paper reports that dead-load and live-load weight in the main and side spans is balanced using concrete ballast placed in the maintenance walkway and main truss chord. This indicates attention to the longitudinal balance of the cable-stayed system and to control of tower and girder force effects. The publicly available abstract does not give the ballast quantities, placement details, load cases or final tuning procedure.
5. Engineering design considerations
5.1 Dead load and traffic load
The permanent weight includes the steel truss, orthotropic deck, surfacing, barriers, utilities, cable system, tower components and reported concrete ballast. Traffic loading acts through the deck and truss and produces a combination of local deck-plate effects and global bridge response. Because the bridge has a cable-supported long span, the distribution of live load between stays, towers, main span, side spans and bearings is an important design issue.
No project-specific traffic load model, lane arrangement for design, fatigue category, design vehicle or load combinations were identified in the accessible technical summaries. The bridge is described as a four-lane highway bridge; this is a geometric/operational fact, not a substitute for the design loading specification.
5.2 Wind and aerodynamic stability
Wind is particularly important for long-span bridges and for construction stages when the partially erected girder has less structural continuity and different mass and stiffness than the completed bridge. The designers studied mountain wind loading, according to the published project paper. Relevant checks for a bridge of this type generally include static wind forces, buffeting response, vortex-induced vibration, flutter, torsional response, tower-girder-cable interaction and wind effects during erection. These describe engineering considerations and should not be read as a verified list of project analyses unless confirmed in full design records.
5.3 Seismic response and stability
A cable-stayed bridge’s seismic response depends on the dynamic interaction of towers, stays, girder, bearings and foundations. Different support heights and stiffnesses can produce complex modes. The project’s seismic design parameters and detailing are not disclosed in the accessible sources reviewed here. Any retrofit or safety assessment would need the original model, local seismic hazard, bearing and damper details, and current inspection data.
5.4 Cable forces, deflection and construction stages
Stay cables transfer tensile forces from the deck to the pylons. Their force and geometry change as deck segments are added, cables are installed and stressed, ballast is placed, and closure is achieved. The completed geometry is therefore the outcome of staged construction analysis rather than a single static configuration. Cable tension, deck camber, tower displacement, segment geometry and temperature must be coordinated during erection.
The source confirms that stay cable freezing monitoring was considered for operation. It does not publish a monitoring layout, alarm threshold, field measurements or anti-icing details.
5.5 Foundations, settlement and durability
The pile groups transfer tower compression, horizontal force and overturning effects into the ground. In variable karst terrain, the relevant design and construction concerns include pile integrity, variability in rockhead, groundwater, local cavities, group interaction, differential movement and slope stability. The paper reports pile number and diameter, but not design capacity or settlement values.
Durability considerations for this structural form include corrosion protection of exposed steelwork and cables, drainage and waterproofing of the orthotropic deck, fatigue management at welded details, concrete protection and inspection access to anchorages. These are normal engineering requirements for the system; public sources reviewed do not provide a detailed project durability specification or condition assessment.
6. Construction methodology
The following sequence combines reported project details with a conventional interpretation of the structural sequence. Steps marked as documented are explicitly supported by project or construction reporting. Other steps are presented as the likely engineering sequence and must not be mistaken for a complete method statement.
6.1 Survey, site preparation and access (general sequence). Establish control networks on both sides of the gorge, develop access roads and working platforms, and prepare lifting and material handling areas. Exact access works and survey procedures were not found in the public sources reviewed.
6.2 Geological investigations and foundation planning (documented constraint; sequence inferred). Investigate steep terrain and karst conditions to guide tower placement and foundation design. The project literature confirms geology as a key constraint but does not publish investigation logs or treatment details.
6.3 Pile-group foundations (documented configuration). Construct the 28-pile foundation groups reported for the tower supports, with each pile 2.8 m in diameter. The exact piling technique, casing, reinforcement cage arrangement, pile lengths, rock sockets and testing regime are not available from the reviewed abstracts. Read our in-depth article on Pile Foundations: Types of Piles for Foundations.
6.4 Tower construction (documented). Build the reinforced-concrete H-shaped towers. Potain tower cranes were reported in use for tower construction. The crane transport journey and narrow mountain access demonstrate the logistics burden. Concrete placement methods, tower lift heights, and formwork details are not confirmed here.
6.5 Steelwork fabrication and delivery (general sequence). Fabricate truss segments, orthotropic deck elements, anchorage boxes and associated steelwork, then deliver components to the gorge-side erection areas. Public summaries identify the steel truss and deck system but do not describe the fabrication yards or complete QA records.
6.6. Steel Truss Girder Erection Using Longitudinal Launching and Cantilever Construction: The erection of the steel truss girder was one of the major construction challenges of the Beipanjiang Bridge. Due to the approximately 565 m deep gorge, steep terrain and limited access, conventional ground-supported falsework was impractical. Instead, a specialised longitudinal launching and cantilever erection arrangement was adopted, allowing the steel truss girder to advance across the gorge with minimal dependence on ground-level temporary supports.
The system incorporated under-bridge rail arrangements to guide and support the advancing steel truss segments during erection. Successive segments were assembled and progressively advanced along the bridge alignment. Surveying was essential to maintain the required girder elevation, longitudinal alignment and connection geometry, while accounting for construction-stage deformation and temperature variations.
Stay-cable installation and stressing were coordinated with girder erection to maintain structural equilibrium and the required geometry. Each construction stage required consideration of temporary loads, including the self-weight of steel segments, construction equipment, wind forces and unbalanced cantilever loading. Particular attention was necessary to ensure lateral stability, control deformation and prevent excessive stresses in the partially completed structure.
6.7 Stay-cable installation and stressing (structural sequence inferred; system documented). Install cable pairs progressively as the girder advances, connect to tower anchor beams and truss anchor boxes, and adjust forces to maintain the target geometry and staged equilibrium. The exact stressing order and target forces are not public in the sources reviewed.
6.8 Closure and final integration (documented milestone). The bridge was joined/closed in September 2016, according to project reporting, before opening to traffic on 29 December 2016. The exact closure location, temperature correction and final geometry records are unavailable.
6.9 Deck completion, finishing and commissioning (general sequence). Complete surfacing, barriers, drainage, road equipment, inspection and load/operational acceptance. Public sources confirm the bridge opened to traffic but do not provide the test vehicle arrangement or acceptance report.
Construction methodology summary
| Work stage | Method or feature | Evidence status |
|---|---|---|
| Towers | Reinforced-concrete H-shaped towers; tower cranes used | Documented in engineering abstract and construction trade reporting |
| Foundations | 28 piles per reported tower foundation group, 2.8 m diameter | Engineering paper abstract |
| Main girder | Steel truss with orthotropic steel deck | Engineering paper abstract |
| Segment erection | Longitudinal launching and cantilever construction with under-bridge rails | Engineering project descriptions |
| Segment lifting | No independently confirmed segment lifting equipment specified here | Project-specific method statements were not available |
| Cable system | 224 stays, arranged as 112 pairs, anchored to tower beams and truss anchor boxes | Engineering paper abstract |
| Completion | Closure reported in September 2016; public opening on 29 December 2016 | Project and government reporting |
7. Materials and quality control
7.1 Materials reported
The sources reviewed identify reinforced concrete towers, steel truss members, an orthotropic steel deck, stay cables, steel tower anchorage beams, steel truss anchor boxes and concrete ballast. Specific material grades, cable strand type, wire strength, coating system, concrete strength classes, reinforcing steel grade and fatigue detail categories were not available in the public abstracts and official summaries consulted for this case study.
7.2 Quality assurance topics for this structural system
A project-specific quality plan would typically control the following. This is a recommended engineering checklist, not confirmation that each procedure was used in this exact form on the project:
- Concrete: mix qualification, delivery and temperature control, slump/workability, strength specimens, curing, reinforcement cover, construction joints, tower geometry and concrete defect repair.
- Piles: drilling records, strata and groundwater logs, bore stability, reinforcement cage checks, concrete volume and placement continuity, integrity testing and load testing as specified by design.
- Steel fabrication: material traceability, dimensional tolerances, fit-up, welding procedure qualification, welder qualification, weld visual inspection and specified non-destructive examination.
- Orthotropic deck: plate and rib geometry, weld quality, flatness, drainage details, surfacing interface and fatigue-sensitive details.
- Stay cables and anchorages: strand or wire traceability, corrosion protection, socket/anchorage inspection, installation geometry, stressing calibration, force verification and sealing of anchorage zones.
- Erection control: survey of segment position, temporary support forces, cable tensions, tower movements, wind limits, bolt/weld completion and closure geometry.
- Commissioning: bearing and joint checks, roadway safety equipment, inspection access, baseline geometry and any specified load or dynamic acceptance tests.
No project-specific non-destructive testing report, concrete test results, steel certificates, cable force logs or commissioning test data were located in the public sources reviewed. These quality items are listed to guide interpretation and further research, not to imply that records are missing from the project owner’s archives.
8. Major engineering challenges and solutions
| Challenge | Why it mattered | Documented response | Engineering contribution/interpretation |
|---|---|---|---|
| Very deep gorge and steep valley sides | Ground-supported falsework across the gorge would be impractical and could create major temporary works and access risks | A long-span cable-stayed layout carries the deck from towers founded on opposite sides; steel truss erection used a purpose-designed launching/cantilever system | Keeps the primary load path above the gorge and limits dependence on riverbed access |
| Karst and complex geology | Variable ground conditions complicate foundation design and construction | Project sources report investigations and design studies responsive to karst and complex terrain; tower foundations use large-diameter pile groups | Foundation performance depends on site-specific investigation and construction records, which are not public in the reviewed sources |
| Mountain wind environment | Terrain can alter wind speed, direction and turbulence; partly built structures may be especially sensitive | Wind loading in mountainous areas was a stated design study topic | Supports the need for site-specific aerodynamic analysis and erection-stage wind management; numerical criteria are unavailable |
| Delivery and access constraints | Large equipment and materials had to reach a remote mountain site | Tower cranes were transported over 2,000 km, including narrow and winding access roads | Early logistics and equipment selection were structural project-planning issues, not merely procurement details |
| Main-girder erection over the gorge | Conventional component-by-component erection can be slow and difficult where access below the deck is unavailable | Engineering reporting describes longitudinal launching/cantilever erection with under-bridge rails; further lifting equipment details were not verified | Segment-level handling can reduce repeated individual member lifts, but temporary-stage stability and geometry control remain critical |
| Cable icing during service | Ice can affect cable operation, loads and maintenance safety in cold conditions | Cable-freezing monitoring technology was reported as a project study | Demonstrates that environmental effects continue after opening; the actual monitoring system and thresholds are not publicly detailed |
9. Structural performance and maintenance
The project design paper states that the bridge was in good operational condition at the time of its 2018 publication. This is a qualitative statement, not a published condition survey or a time-series performance record. No verified long-term measurements of deflection, cable force, vibration, fatigue, corrosion, settlement or seismic performance were located for this case study.
For a long-span steel-truss cable-stayed bridge, a maintenance regime should give particular attention to:
- cable sheaths, anchorage seals, water ingress, corrosion and local cable vibration;
- steel truss members, connections, welds and fatigue-sensitive details;
- orthotropic deck plate, rib welds, surfacing, drainage and leakage;
- reinforced-concrete tower surfaces, cracking, joints, drainage and reinforcement corrosion risk;
- bearings, expansion joints, barriers and approach transitions;
- foundation and slope movement, erosion and drainage around tower sites;
- monitoring systems, sensor calibration, data continuity and alarm response.
The published work specifically mentions cable freezing monitoring. It is reasonable to infer that monitoring and inspection are important because of the cable system, extreme site exposure and difficult access, but the actual instrumentation scheme must be confirmed from owner documents. A maintenance plan should combine scheduled visual inspection with targeted close-up inspection, cable and anchorage assessment, structural monitoring where installed, and risk-based access planning.
10. Engineering analysis and lessons learned
10.1 Why the structural system is efficient
A cable-stayed bridge is suited to this crossing because the gorge is too deep for intermediate piers and the abutments are separated by a long distance. Two towers and stay cables provide intermediate support points along the deck. The steel truss supplies longitudinal stiffness and a constructible framework for segmental erection. This combination makes it possible to bridge the gorge without placing supports in the river or valley floor.
The long 720 m main span is supported by the arrangement of pylons, stays, side spans and ballast. The reported ballast strategy indicates that force balance and overall system equilibrium were considered as part of the design. The specific efficiency or material savings cannot be quantified without comparative designs and bill-of-quantities data.
10.2 Lessons for mountainous and seismic regions, including Bhutan and the Himalayas
- Select the bridge type from terrain and access constraints. A bridge system should be evaluated together with foundation access, temporary works, transport routes and construction-stage stability. A technically elegant superstructure is not buildable if the site cannot receive the required components and equipment.
- Treat construction stages as design situations. In long-span cable-supported bridges, the partial structure can have very different stiffness and wind response from the completed bridge. Stage-by-stage analysis, erection limits and geometry control need to be integrated early.
- Investigate the ground as a three-dimensional system. In karst and steep terrain, tower foundations and slopes interact. Boreholes alone may not describe all cavities, discontinuities, groundwater routes or slope movement risks. Investigation should be adapted to geology and checked against conditions encountered during excavation and piling.
- Use modular erection where access below the span is unavailable. Segmental fabrication and launching systems can reduce reliance on valley-floor access. The method must be supported by temporary works design, lifting analysis, wind limits, redundancy and clear rescue arrangements.
- Design for maintenance access from the outset. Cable anchorage areas, deck inspection points, tower access, drainage and sensor maintenance can be difficult at extreme heights. A bridge that is buildable but not safely inspectable creates a long-term asset-management problem.
- Do not transfer design parameters by analogy. The project is a useful precedent, but Himalayan bridges require local seismic hazard, wind climatology, snow and ice assessment, geology, materials supply, construction capability and maintenance planning. The Duge design values, where later found, should not be copied without site-specific analysis.
These are engineering interpretations drawn from the documented structural form and site constraints. They are not claims that the Duge project used a particular analysis method or that its detailed solutions can be directly applied to every Himalayan crossing.
11. Conclusion
The Beipanjiang Bridge demonstrates how a steel-truss cable-stayed system can connect steep mountainous terrain across an exceptionally deep gorge. Its 720 m main span, paired stay-cable system, reinforced-concrete H-shaped towers and pile-group foundations form an integrated structural solution. The project’s most instructive aspects are the coordination of long-span design with complex terrain, wind studies, logistics and specialized girder erection.
The project also illustrates an important limit of public project descriptions: headline dimensions and construction innovations are much easier to verify than design loads, material grades, foundation capacity, test results or long-term monitoring data. For engineers, the bridge is best studied as a documented structural concept and construction case, while project-specific calculations and performance claims should await access to original records.
Frequently Asked Questions
Q: What type of bridge is the Beipanjiang Bridge?
It is a two-pylon cable-stayed bridge with a steel truss main girder and an orthotropic steel deck. It is not a suspension bridge.
Q: How long is the main span of the Duge Bridge?
The central main span is 720 m. The reported total bridge length is 1,341.4 m.
Q: How high is the Beipanjiang Bridge above the river?
The roadway clearance is commonly reported as about 565 m. Guinness World Records specifies 565 m above mean high water. Other sources use valley-floor or river-height wording, so the measurement datum should be stated.
Q: How is the bridge deck supported?
Stay cables connect the steel truss deck to two reinforced-concrete towers. The cables carry tension, the towers transfer forces to their pile foundations, and the truss distributes deck loads longitudinally.
Q: What foundations were used for the bridge towers?
The 2018 engineering paper abstract reports a group of 28 piles, each 2.8 m in diameter, for the tower foundations. Publicly accessible summaries reviewed here do not specify the pile lengths, socket details or capacities.
Q: How was the steel truss erected across the gorge?
Published descriptions report longitudinal launching and cantilever erection using under-bridge rails. No project-specific evidence for cable-crane lifting was found in the sources reviewed. The full erection method statement and stage-by-stage records were not publicly available.
Q: Is the Beipanjiang Bridge still the world’s highest bridge?
It is no longer the highest bridge overall. The Huajiang Grand Canyon Bridge opened in 2025 and was certified by Guinness in 2026 at 626.01 m, overtaking Beipanjiang’s 565 m overall record. Beipanjiang remains listed by Guinness as the highest cable-stayed bridge. Record comparisons depend on the measurement definition, so specify whether the comparison concerns roadway clearance, deck elevation or tower height.
Research Limitations and Data Availability
Information verified from primary or near-primary project sources
- The 2018 engineering paper by Liu, Peng and Hou provides the main structural arrangement, span sequence, girder type, cable count and anchorage arrangement, tower form, pile count/diameter, and design study topics.
- PIARC’s 2017 Routes/Roads article by Liu Bo identifies project design and construction as its subject and gives the total length and main span.
- Guinness World Records gives the record definition, 565 m mean-high-water clearance, 1,341 m total length, 720 m longest span and opening date.
- Guizhou government-linked reporting confirms the boundary location, 1,341.4 m total length, 720 m main span and December 2016 opening.
Information drawn from secondary or trade sources
Construction contractor attribution, crane logistics, selected segment erection details, the construction start period, designer attribution and cost reports come from construction trade publications or Chinese project reporting rather than a complete owner-issued project dossier. Where those sources differ or lack scope definitions, this article avoids presenting a definitive contractual account.
Records not publicly available in the sources reviewed
The reviewed sources do not include original general arrangement drawings, design calculations, load combinations, material grades, detailed geotechnical logs, pile lengths and capacities, seismic design parameters, wind-tunnel data, fabrication inspection plans, cable stressing records, closure geometry logs, acceptance load tests, full instrumentation layout or long-term condition monitoring results.
Further investigation needed
A publication seeking design-level detail should obtain the owner’s as-built drawings and inspection records, the design consultant’s technical report, the construction method statement and temporary works calculations, material and weld QA records, foundation investigation and pile testing documentation, and current asset-management reports. No physical site inspection was conducted for this case study.
References and further reading
- Liu, B., Peng, Y.-D. and Hou, M. (2018). “Design and Key Technology of Main Bridge of Beipanjiang Bridge.” Bridge Construction, 48(6), 81–86. Project paper abstract and bibliographic details: ResearchGate record. Chinese title: 贵州都格北盘江大桥主桥设计及关键技术.
- Liu, Bo (2017). “Design and Construction of the Beipanjiang Bridge.” Routes/Roads, No. 374, September 2017, PIARC. Article page and PIARC publication record.
- Bo, L., Peng, Y. and Hou, M. (2018). “Design and Construction of Beipanjiang Bridge.” IABSE Conference, Kuala Lumpur 2018: Engineering the Developing World, pp. 505–512. Bibliographic record and abstract: EurekaMag record.
- Guinness World Records. “Highest cable-stayed bridge.” Beipanjiang Bridge Duge, record page. Record definition and dimensions. Accessed 8 November 2026.
- Wang, D. and Chen, Z. (2024). “Guizhou’s five record-setting bridges.” China Daily / eGuizhou, 24 September 2024. Government-linked provincial article.
- “Work begins on Duge Beipanjiang Bridge towers.” Bridge Design & Engineering, 2013. Construction reporting on tower cranes, access logistics and main contractor. Article.
- “The Beipanjiang First Bridge.” Infrastructure Global. Engineering project overview describing longitudinal launching and cantilever erection with under-bridge rails. Project page.
- “Beipanjiang set Guinness record as highest bridge.” State Council Information Office of China, 21 September 2018. Government report.
- Xinhua (2026). “China’s Huajiang Grand Canyon Bridge certified as world’s highest.” Report of Guinness certification and updated overall record.
![]()